M.P. Power Generating Co. Ltd
True Up Petition For FY 07   Schedule- 3i  
Summary of Generation & Generation Cost
As Per Tariff Order
S. No. Particulars Capacity Details For 12 Months
Installed MPPGCL Share Net Gen Fixed Cost Variable Cost Total Cost
MW % MW MU L Rs L Rs/MW p/u L Rs p/u L Rs p/u
1 Thermal Generation ATPS Chachai PH 1 50.0 100% 50.0                
2 ATPS Chachai PH 2 240.0 100% 240.0                
3 ATPS Chachai Complex 290.0 100% 290.0 1150 4738 16.34 41 13451 117 18189 158
4 STPS Sarni PH 1 312.5 60% 187.5                
5 STPS Sarni PH 2 410.0 100% 410.0                
6 STPS Sarni PH 3 420.0 100% 420.0                
7 STPS Sarni Complex 1142.5 89% 1017.5 7076 20154 17.64 28 95526 135 115680 163
8 SGTPs Birsinghpur PH 1 420.0 100% 420.0                
9 SGTPs Birsinghpur PH 2 420.0 100% 420.0                
10 SGTPs Birsinghpur Complex 840.0 100% 840.0 5021 30294 36.06 60 51716 103 82010 163
11 Total 2272.5 94% 2147.5 13247 55186 24.28 42 160693 121 215879 163
S. No. Particulars Capacity Details For 12 Months
Installed MPPGCL Share Net Gen Fixed Cost Variable Cost Total Cost
MW % MW MU L Rs L Rs/MW p/u L Rs p/u L Rs p/u
1 Hydro Stations Gandhi Sagar 115.0 50% 57.5 343 1037 9.02 30     1037 30
2 Pench  160.0 67% 106.7 313 1116 6.98 36     1116 36
3 Bir'pur Hydl 20.0 100% 20.0 45 387 19.35 87     387 87
4 Ban Sagar 405.0 100% 405.0 1094 9370 23.14 86     9370 86
5 Bargi 90.0 100% 90.0 503 945 10.50 19     945 19
6 Rajghat 45.0 50% 22.5 89 850 18.89 95     850 95
7 Jawahar Sagar 99.0 50% 49.5                
8 RP Sagar 172.0 50% 86.0                
9 Total  1106.0 76% 837.2 2386 13705 12.39 57     13705 57
Total  3378.5 88% 2984.7 15633 68891   44 160693 103 229584 147