| ANALYSIS OF FORCED OUTAGES - SGTPS BIRSINGHPUR 2009-10 | ||||||||
| APRIL | ||||||||
| S.N. | DETAILS | DATE OF SHUTDOWN | DATE OF SYNCH. | PERIOD IN HOURS | MU LOST | REASON | CORRECTIVE ACTION TAKEN | |
| PLANNED | ||||||||
| 1 | UNIT-1 | 0.00 | 0.00 | |||||
| 2 | UNIT-2 | 0.00 | 0.00 | |||||
| 3 | UNIT-3 | 0.00 | 0.00 | |||||
| 4 | UNIT-4 | 0.00 | 0.00 | |||||
| FORCED | ||||||||
| 1 | UNIT-1 | 25.04.2009 | 27.04.2009 | 38.55 | 8.17 | Economiser Tube Leakage | Tube replaced , hydraulic done, Unit Synchronised. | |
| 2 | UNIT-2 | 22.04.2009 | 22.04.2009 | 3.22 | 0.71 | Furnace Pressure Low | Getting normal parameters, Unit synchronised. | |
| 3 | UNIT-3 | NO TRIPPING | ||||||
| UNIT-4 | NO TRIPPING | |||||||
| UNIT-5 | 01.04.2009 | 01.04.2009 | 6.55 | 3.46 | Clinker Formation | Clinker removed,Unit synchronised | ||
| 27.04.2009 | 27.04.2009 | 4.15 | 2.13 | Flame Failure | Getting normal parameters, Unit synchronised. | |||
| 29.04.2009 | 29.04.2009 | 2.44 | 1.37 | Primary Water Flow Low | Getting normal parameters, Unit synchronised. | |||
| TOTAL | 54.91 | 15.84 | ||||||
| MAY | ||||||||
| S.N. | DETAILS | DATE OF SHUTDOWN | DATE OF SYNCH. | PERIOD IN HOURS | MU LOST | REASON | CORRECTIVE ACTION TAKEN | |
| PLANNED | ||||||||
| 1 | UNIT-1 | 0.00 | 0.00 | |||||
| 2 | UNIT-2 | 0.00 | 0.00 | |||||
| 3 | UNIT-3 | 0.00 | 0.00 | |||||
| 4 | UNIT-4 | 0.00 | 0.00 | |||||
| FORCED | ||||||||
| 1 | UNIT-1 | 14.05.2009 | 15.05.2009 | 17.35 | 3.69 | Economiser Tube Leakage | Tube replaced , hydraulic done, Unit Synchronised. | |
| 21.05.2008 | 23.05.2008 | 55.25 | 11.64 | Economiser Tube Leakage | Tube replaced , hydraulic done, Unit Synchronised. | |||
| 2 | UNIT-2 | 25.05.2008 | 25.05.2008 | 4.45 | 1.00 | Boiler MCC MC Tripped | After attending fault , Unit synchronised. | |
| 3 | UNIT-3 | 14.05.2009 | 16.05.2009 | 61.05 | 12.83 | Boiler Tube Leakage | Tube replaced , hydraulic done, Unit Synchronised. | |
| 4 | UNIT-4 | 10.05.2009 | 10.05.2009 | 5.05 | 1.07 | Electrical system, 220 KV heavy jerk. | After attending fault , Unit synchronised. | |
| 5 | UNIT-5 | 04.05.2009 | 04.05.2009 | 3.51 | 1.93 | Flame Failure | Getting normal parameters, Unit synchronised. | |
| 10.05.2009 | 10.05.2009 | 3.10 | 1.58 | System Jerk | After attending fault , Unit synchronised. | |||
| TOTAL | 149.76 | 33.74 | ||||||
| JUNE | ||||||||
| S.N. | DETAILS | DATE OF SHUTDOWN | DATE OF SYNCH. | PERIOD IN HOURS | MU LOST | REASON | CORRECTIVE ACTION TAKEN | |
| PLANNED | ||||||||
| 1 | UNIT-1 | 0.00 | 0.00 | |||||
| 2 | UNIT-2 | 0.00 | 0.00 | |||||
| 3 | UNIT-3 | 0.00 | 0.00 | |||||
| 4 | UNIT-4 | 0.00 | 0.00 | |||||
| FORCED | ||||||||
| 1 | UNIT-1 | 22.06.2009 | 25.06.2009 | 60.51 | 12.78 | I. D. Fan Vibration | After attending fault , Unit synchronised. | |
| 2 | UNIT-2 | 01.06.2009 | 03.06.2009 | 63.18 | 13.29 | Reheater Tube Leakage | Tube replaced , hydraulic done, Unit Synchronised. | |
| 08.06.2009 | 08.06.2009 | 2.05 | 0.44 | Attending Bus -I Isolator | After attending fault , Unit synchronised. | |||
| 10.06.2009 | 10.06.2009 | 0.35 | 0.12 | Attending Bus -I Isolator | After attending fault , Unit synchronised. | |||
| 14.06.2009 | 19.06.2009 | 101.35 | 21.33 | Economiser Tube Leakage | Tube replaced , hydraulic done, Unit Synchronised. | |||
| 3 | UNIT-3 | 09.06.2009 | 10.06.2009 | 4.30 | 0.95 | Y Phase Isolator alignment | After attending fault , Unit synchronised. | |
| 18.06.2009 | 21.06.2009 | 73.20 | 15.40 | Boiler Tube Leakage | Tube replaced , hydraulic done, Unit Synchronised. | |||
| 27.06.2009 | A.O.H. | |||||||
| 4 | UNIT-4 | 05.06.2009 | 07.06.2009 | 51.00 | 10.71 | Boiler Tube Leakage | Tube replaced , hydraulic done, Unit Synchronised. | |
| UNIT-5 | 04.06.2009 | 04.06.2009 | 3.00 | 1.58 | E2 Valve Closed | After attending fault , Unit synchronised. | ||
| TOTAL | 358.94 | 76.60 | ||||||