ANALYSIS OF FORCED OUTAGES -  SGTPS  BIRSINGHPUR   2009-10
 
APRIL
S.N. DETAILS DATE OF SHUTDOWN DATE OF SYNCH. PERIOD IN HOURS MU  LOST REASON CORRECTIVE ACTION TAKEN
  PLANNED
1 UNIT-1     0.00 0.00    
2 UNIT-2     0.00 0.00    
3 UNIT-3     0.00 0.00    
4 UNIT-4     0.00 0.00    
  FORCED
1 UNIT-1 25.04.2009 27.04.2009 38.55 8.17 Economiser Tube Leakage Tube replaced , hydraulic done, Unit Synchronised.
2 UNIT-2 22.04.2009 22.04.2009 3.22 0.71 Furnace Pressure Low Getting normal parameters, Unit synchronised.
3 UNIT-3         NO TRIPPING  
  UNIT-4         NO TRIPPING  
  UNIT-5 01.04.2009 01.04.2009 6.55 3.46 Clinker Formation Clinker removed,Unit synchronised
  27.04.2009 27.04.2009 4.15 2.13 Flame Failure Getting normal parameters, Unit synchronised.
  29.04.2009 29.04.2009 2.44 1.37 Primary Water Flow Low Getting normal parameters, Unit synchronised.
  TOTAL     54.91 15.84    
   
   
   
MAY
S.N. DETAILS DATE OF SHUTDOWN DATE OF SYNCH. PERIOD IN HOURS MU  LOST REASON CORRECTIVE ACTION TAKEN
  PLANNED
1 UNIT-1     0.00 0.00    
2 UNIT-2     0.00 0.00    
3 UNIT-3     0.00 0.00      
4 UNIT-4     0.00 0.00    
  FORCED
1 UNIT-1 14.05.2009 15.05.2009 17.35 3.69 Economiser Tube Leakage Tube replaced , hydraulic done, Unit Synchronised.
21.05.2008 23.05.2008 55.25 11.64 Economiser Tube Leakage Tube replaced , hydraulic done, Unit Synchronised.
2 UNIT-2 25.05.2008 25.05.2008 4.45 1.00 Boiler MCC MC Tripped After attending fault , Unit synchronised.
3 UNIT-3 14.05.2009 16.05.2009 61.05 12.83 Boiler Tube Leakage Tube replaced , hydraulic done, Unit Synchronised.
4 UNIT-4 10.05.2009 10.05.2009 5.05 1.07 Electrical system, 220 KV heavy jerk. After attending fault , Unit synchronised.
5 UNIT-5 04.05.2009 04.05.2009 3.51 1.93 Flame Failure Getting normal parameters, Unit synchronised.
10.05.2009 10.05.2009 3.10 1.58 System Jerk After attending fault , Unit synchronised.
  TOTAL     149.76 33.74    
JUNE
S.N. DETAILS DATE OF SHUTDOWN DATE OF SYNCH. PERIOD IN HOURS MU  LOST REASON CORRECTIVE ACTION TAKEN
  PLANNED
1 UNIT-1     0.00 0.00    
2 UNIT-2     0.00 0.00    
3 UNIT-3     0.00 0.00    
4 UNIT-4     0.00 0.00    
  FORCED
1 UNIT-1 22.06.2009 25.06.2009 60.51 12.78 I. D. Fan   Vibration After attending fault , Unit synchronised.
2 UNIT-2 01.06.2009 03.06.2009 63.18 13.29 Reheater Tube Leakage Tube replaced , hydraulic done, Unit Synchronised.
08.06.2009 08.06.2009 2.05 0.44 Attending Bus -I Isolator After attending fault , Unit synchronised.
10.06.2009 10.06.2009 0.35 0.12 Attending Bus -I Isolator After attending fault , Unit synchronised.
14.06.2009 19.06.2009 101.35 21.33 Economiser Tube Leakage Tube replaced , hydraulic done, Unit Synchronised.
3 UNIT-3 09.06.2009 10.06.2009 4.30 0.95 Y Phase Isolator alignment After attending fault , Unit synchronised.
18.06.2009 21.06.2009 73.20 15.40 Boiler Tube Leakage Tube replaced , hydraulic done, Unit Synchronised.
27.06.2009       A.O.H.  
4 UNIT-4 05.06.2009 07.06.2009 51.00 10.71 Boiler Tube Leakage Tube replaced , hydraulic done, Unit Synchronised.
  UNIT-5 04.06.2009 04.06.2009 3.00 1.58 E2 Valve Closed After attending fault , Unit synchronised.
  TOTAL     358.94 76.60