ANALYSIS OF FORCED OUTAGES -  SGTPS  BIRSINGHPUR   2009-10
 
JULY
S.N. DETAILS DATE OF SHUTDOWN DATE OF SYNCH. PERIOD IN HRS:MIN MU  LOST REASON CORRECTIVE ACTION TAKEN
  PLANNED
1 UNIT-1     0.00 0.00    
2 UNIT-2     0.00 0.00    
3 UNIT-3 27.06.2009 30.07.2009 784:57 164.84 A.O.H.  
4 UNIT-4     0.00 0.00    
  FORCED
1 UNIT-1   (210 MW) 19.07.2009 19.07.2009 04:20 0.91 Stator water Conductivity high Getting normal parameters, Unit synchronised.
20.07.2009 21.07.2009 04:53 1.03 Furnace Pressure Low Getting normal parameters, Unit synchronised.
23.07.2009 25.07.2009 31:32 6.62 Economiser Tube Leakage Leakage attended. Unit Synchronised.
2 UNIT-2   (210 MW) 14.07.2009 14.07.2009 05:37 1.18 Furnace Pressure Low Getting normal parameters, Unit synchronised.
29.07.2009 29.07.2009 06:24 1.34 Generator Breaker Tripped. After attending fault, Unit synhronised.
3 UNIT-3   (210 MW) 27.06.2009 30.07.2009 784:57 164.84 A.O.H.  
30.07.2009 30.07.2009 04:30 0.95 False operation of Over Current Relay Relay reset. Unit synchronised.
4 UNIT-4   (210 MW) NO TRIPPING
5 UNIT-5   (500 MW) 09.07.2009 09.07.2009 03:49 1.91 UPS 1&2 Failure Clinker removed,Unit synchronised
23.07.2009 23.07.2009 05:44 2.87 Flame Failure Getting normal parameters, Unit synchronised.
  TOTAL       181.65    
   
   
   
AUGUST
S.N. DETAILS DATE OF SHUTDOWN DATE OF SYNCH. PERIOD IN HOURS MU  LOST REASON CORRECTIVE ACTION TAKEN
PLANNED
1 UNIT-1     0.00 0.00    
2 UNIT-2     0.00 0.00    
3 UNIT-3     0.00 0.00      
4 UNIT-4     0.00 0.00    
FORCED
1 UNIT-1   (210 MW)         NO  TRIPPING  
2 UNIT-2    (210 MW) 07.08.2009 07.08.2009 02:21 0.49 Furnace Pressure Low Getting normal parameters, Unit synchronised.
26.08.2009 31.08.2009 132:56 27.92 Platen S/H & Economiser Tube Leakage Tube replaced , hydraulic done, Unit Synchronised.
3 UNIT-3   (210 MW)         NO  TRIPPING  
4 UNIT-4   (210 MW)         NO  TRIPPING  
5 UNIT-5   (500 MW) 03.08.2009 01.09.2009 696:00 348.00 A.O.H.  
  TOTAL       376.41    
SEPTEMBER
S.N. DETAILS DATE OF SHUTDOWN DATE OF SYNCH. PERIOD IN HOURS MU  LOST REASON CORRECTIVE ACTION TAKEN
PLANNED
1 UNIT-1     0.00 0.00    
2 UNIT-2 14.09.2009   0.00 0.00 A.O.H.  
3 UNIT-3     0.00 0.00    
4 UNIT-4 04.09.2009   0.00 0.00 A.O.H.  
FORCED
1 UNIT-1    (210 MW) 11.09.209 15.09.2009 87:13 18.32 Unit stopped for AOH & lateron AOH cancelled. After maintenance work , Unit synchronised.
23.09.2009 27.09.2009 95:20 20.02 Both ID Fan high vibration & Tube leakage. After maintenance work , Unit synchronised.
2 UNIT-2    (210 MW) 12.09.2009 14.09.2009 29:52 6.27 Casing damaged. Tube replaced , hydraulic done, Unit Synchronised.
3 UNIT-3    (210 MW) 03.09.2009 05.09.2009 37:54 7.96 False operation of Over Current Relay After resetting relay , Unit synchronised.
15.09.2009 17.09.2009 50:43 10.65 Economiser Tube Leakage Tube replaced , hydraulic done, Unit Synchronised.
19.09.2009 23.09.2009 101:22 21.29 Economiser Tube Leakage Tube replaced , hydraulic done, Unit Synchronised.
28.09.2009 29.09.2009 28:49 6.05 False operation of Over Current Relay After resetting relay , Unit synchronised.
4 UNIT-5    (500 MW) 01.09.2009 01.09.2009 6:36 3.30 Turbine Bearing Temp. high After attending fault , Unit synchronised.
09.09.209 11.09.209 42:40 21.33 Air Heater duct leakage After maintenance work , Unit synchronised.
17.09.2009 22.09.2009 114:22 57.18 Boiler Tube Leakage Tube replaced , hydraulic done, Unit Synchronised.
  TOTAL       172.37