IN THE HON’BLE SUPREME COURT , NEW DELHI W.P. NO. 202/95 & W.P. NO. 171/96 |
||||||||||||||||||||||||||||
|
Petitioner
-
M/S INDIAN ENTERPRISES,
NAGPUR
V/s Respondent
-
M.P.S.E.B. & OTHERS GIST
OF THE CASE- STATEMENT OF STATUS
Grounds
taken by applicant while involving MPEB:-
That the MPEB was well aware about section 1.7 (i) of rules and
guidelines of Forest Conservation Act 1980, that lease or sublease of
Forest Land, land is not permitted without prior approval of forest
along with MPEB issued NOC of 5.534 hectare to the WCL on 10-10-1995. Brief
History of the Matter:-
The State Government has accorded sanction to transfer of an area
of 4695.83 Acres of forest land near Sarni forest village in North Betul
division to the MPEB for the construction of Thermal Power Station.
Notice this effect was published in M.P. Govt. Gazette dated
05-01-1968. Out of the said land, the Board has issued No Objection Certificates for two pieces of adjoining land tabulated as under to M/s WCL, Nagpur on their request for development of their mining activities.
WCL, Nagpur awarded work of construction of residential quarters
on the aforesaid land to M/s Indian Enterprises, Nagpur on 26-04-1996.
But the said work was stopped by the forest department stating
that the work cannot be commenced without approval of forest
authorities. Present Status of the Case:- The case was heard on 15-09-2004. The reply in favour of Board has been submitted by Shri Satish Agnihotri, the Counselor. After hearing, the matter has been adjourned on the request of the petitioner for filing its response. |